The arbitrators shall determine all controversies between the parties growing out of the contract, including the question whether it had been performed at the time claimed by the contractor and whether the additional work required by the director as specified has been done, and if not done they shall specify the particulars in which it has not been done, give appropriate directions with reference thereto, and shall make a proper award for any extra work they find the contractor entitled to, making such award so far as it is practicable upon the basis of the contract price, having due regard to what is just and equitable between the parties under the facts and circumstances of the case.