Claims against project - Notice of claim - When filed - Where filed
Open in Lexace · Ask the AI about this section
Any person who has furnished labor, materials, or supplies on a contract awarded under 
section 24-02-23, and who has not been paid in full at the time of final acceptance of the project 
by the department, has the right to file a claim against the contractor and the surety furnishing 
the performance bond.

Notice of the claim must be given, in writing, to the contractor or the surety furnishing the 
performance bond and must provide a clear and concise statement of the labor, materials, and 
supplies furnished, to whom it was furnished, and the monetary value thereof. The claim must 
bear interest, on each transaction for labor, materials, or supplies, commencing thirty days after 
the last transaction. The rate of interest must be the rate provided in section 28 -20-34. The 
notice of the claim must be made by certified mail postage prepaid, in an envelope addressed to 
the contractor at any place the contractor maintains an office or has a residence and posted 
within one hundred eighty days from the date on which the person completed the contribution 
giving rise to the claim.