North Dakota Code § 17-05-06

Authority may act
Open in Lexace · Ask the AI about this section
1. The authority shall coordinate its plans for transmission facilities with regional 
organizations having transmission planning responsibilities for the project area.
2. Before exercising its powers to construct transmission facilities granted to it in this 
chapter, the authority shall publish, in a newspaper of general circulation in North 
Dakota and in a newspaper in the project area, a notice describing the need for 
transmission facilities contemplated by the authority. Persons willing to construct the 
transmission facilities or furnish services to satisfy the needs described in the notice 
have a period of one hundred eighty days from the date of last publication of the notice 
within which to deliver to the authority a notice of intent. After receipt of a notice of 
intent, the authority may not exercise its powers to construct transmission facilities 
unless the authority finds that exercising its authority would be in the public interest. In 
making such a finding the authority shall consider factors including economic impact to 
the state, economic feasibility, technical performance, reliability, past performance, and 
the likelihood of successful completion and ongoing operation.
3. The authority may require a person giving a notice of intent to provide a bond and to 
submit a plan for completion of the transmission facilities or commencement of 
services within a period of time acceptable to the authority. If no person submits an 

adequate plan or bond as required by the authority, the authority may proceed with 
contracting for construction of the facility described in the authority's published notice.