58:11-9.6. Renewal of permit, prerequisites to The State department, before it renews any permit, shall be satisfied of the following facts: (a) That the approved physical connection has been tested for tightness under prevailing pressure conditions at least every 3 months; (b) That the approved physical connection has been subjected to an internal inspection within 6 months prior to the application; and (c) That the local board of health, the State department, and the owner of the water supply set forth in section 3 of this act, have determined that the approved physical connection was functioning satisfactorily. L.1942, c. 308, p. 1141, s. 6. Amended by L.1966, c. 47, s. 5, eff. May 24, 1966.
‹ Prev All New Jersey sections Next ›
Lexace provides legal information, not legal advice, and no attorney–client relationship is created. Statute text is provided for general information and may not reflect the most recent amendments; verify against the official state code.