An electric utility shall, upon the completion of construction or acquisition of any electric generating plant or other facility constructed or acquired pursuant to an emissions reduction and capacity replacement plan accepted by the Commission pursuant to NRS 704.751 , begin recording in a regulatory asset, with carrying charges, an amount that reflects a return on the electric utilitys investment in the facility, depreciation of the utilitys investment in the facility and the cost of operating and maintaining the facility.