Nevada Code § 704.706

Conversion of facility to allow firing by coal: Application for adjustment of rates; public hearing
Open in Lexace · Ask the AI about this section
1. A public utility proposing to convert
an existing facility in this state for the generation of electricity which is
fired by gas or oil to a facility which is also capable of being fired by coal
may apply to the Commission for an adjustment in its rates to permit its
recovery of the cost of the conversion.
2. After receipt of such an application,
the Commission shall hold a public hearing within 120 days to consider whether
to authorize such an adjustment and, if authorized, the methods to be used to
permit the recovery.