Nevada Code § 624.890

Contractor who commits certain violations may be required to obtain services of construction control
Open in Lexace · Ask the AI about this section
1. If a contractor who performs work
concerning a residential photovoltaic system used to produce electricity is
determined by the Board to have violated:
(a) One or more of the provisions of NRS 624.301 to 624.305 , inclusive, 624.860 , 624.870 or 624.875 ; or
(b) Any regulation adopted by the Board with
respect to contracts for work concerning a residential photovoltaic system used
to produce electricity,
the Board
may require that the contractor obtain the services of a construction control
for each contract that the contractor enters into for work concerning a
residential photovoltaic system used to produce electricity.
2. The contractor may not:
(a) Be related to the construction control or to
an employee or agent of the construction control; or
(b) Hold, directly or indirectly, a financial
interest in the business of the construction control.
3. As used in this section, construction
control has the meaning ascribed to it in NRS
627.050 .