1. Any person proposing to construct,
reconstruct or alter a dam in this State shall, before beginning construction,
reconstruction or alteration of the dam, obtain approval from the State
Engineer.
2. Any person who obtains approval from
the State Engineer pursuant to subsection 1 shall:
(a) Before constructing, reconstructing or
altering in any way any dam, notify the State Engineer thereof; and
(b) Submit to the State Engineer for approval
plans and specifications for the construction, reconstruction or alteration of
the dam, if the dam:
(1) Is or will be 20 feet or more in
height, measured from the downstream toe to the crest of the dam;
(2) Is less than 20 feet in height and
will impound more than 20 acre-feet of water; or
(3) Is classified by the State Engineer as
a high hazard or significant hazard dam.
3. The State Engineer shall examine any
plans and specifications submitted pursuant to subsection 2 and if approved,
the State Engineer shall return a copy of the plans and specifications with
such approval to the applicant. If the State Engineer disapproves any part of
the plans and specifications the State Engineer shall return them to the
applicant for correction or revision.
4. The construction, reconstruction,
alteration and use of any dam is prohibited before approval by the State
Engineer is obtained pursuant to subsection 1.
5. The State Engineer may at any time
inspect or cause to be inspected the construction, reconstruction or alteration
work on a dam while it is in progress to determine that it is being done in
accordance with the approved plans and specifications, if applicable.
6. The provisions of this section relating
to the approval of plans and specifications and inspection of dams do not apply
to works under the jurisdiction of the United States Bureau of Reclamation or
the United States Army Corps of Engineers, but such federal agencies shall file
duplicate plans and specifications with the State Engineer.
7. Any person beginning the construction,
reconstruction or alteration of any dam before notifying the State Engineer in
accordance with paragraph (a) of subsection 2 or obtaining approval of the
plans and specifications by the State Engineer, if required pursuant to
paragraph (b) of subsection 2, is guilty of a misdemeanor. Each day of
violation of this section constitutes a separate offense and is separately
punishable.

‹ Prev All Nevada sections Next ›


Lexace provides legal information, not legal advice, and no attorney–client relationship is created. Statute text is provided for general information and may not reflect the most recent amendments; verify against the official state code.