1. A claimant or any contractor,
subcontractor, supplier or design professional may submit a question or dispute
to the State Contractors Board concerning any matter which may affect or
relate to a constructional defect, including, without limitation, questions
concerning the need for repairs, the appropriate method for repairs, the sufficiency
of any repairs that have been made and the respective rights and
responsibilities of homeowners, claimants, contractors, subcontractors,
suppliers and design professionals.
2. If a question or dispute is submitted
to the State Contractors Board pursuant to this section, the State
Contractors Board shall, pursuant to its regulations, rules and procedures,
respond to the question or investigate the dispute and render a decision.
Nothing in this section authorizes the State Contractors Board to require the
owner of a residence or appurtenance to participate in any administrative
hearing which is held pursuant to this section.
3. Not later than 30 days after a question
or dispute is submitted to the State Contractors Board pursuant to subsection
1, the State Contractors Board shall respond to the question or render its
decision. The response or decision of the State Contractors Board:
(a) Is not binding and is not subject to judicial
review pursuant to the provisions of chapters
233B and 624 of NRS; and
(b) Is not admissible in any judicial or
administrative proceeding brought pursuant to the provisions of this chapter.
4. The provisions of this chapter do not
preclude a claimant or a contractor, subcontractor, supplier or design
professional from pursuing any remedy otherwise available from the State
Contractors Board pursuant to the provisions of chapter
624 of NRS concerning a constructional defect.
5. If an action for a constructional
defect has been commenced, the court shall not stay or delay any proceedings
before the court pending an answer to a question or decision concerning a
dispute submitted to the State Contractors Board.
6. The State Contractors Board shall
adopt regulations necessary to carry out the provisions of this section and may
charge and collect reasonable fees from licensees to cover the cost of carrying
out its duties pursuant to this section.