Nevada Code § 338.555

Amounts withheld as retainage; payment of interest
Open in Lexace · Ask the AI about this section
1. If a public body and a contractor enter
into a contract for a public work, the contractor may withhold as retainage not
more than 5 percent from the amount of any progress payment due under a
subcontract which is made before 50 percent of the work has been completed
under the subcontract.
2. After 50 percent of the work required
by the contract has been performed, the contractor shall pay any additional
progress payments due under the subcontract without withholding any additional
retainage if, in the opinion of the contractor, satisfactory progress is being
made in the work under the subcontract, and the payment must be equal to that
paid by the public body to the contractor for the work performed by the
subcontractor. If the contractor continues to withhold retainage from remaining
progress payments:
(a) If the contractor does not withhold any
amount pursuant to NRS 338.560 :
(1) The contractor may not withhold more
than 2.5 percent of the amount of any progress payment; and
(2) Before withholding any amount pursuant
to subparagraph (1), the contractor must pay to the subcontractor 50 percent of
the amount of any retainage that was withheld from progress payments pursuant
to subsection 1; or
(b) If the contractor withholds any amount
pursuant to NRS 338.560 :
(1) The contractor may not withhold more
than 5 percent of the amount of any progress payment; and
(2) The contractor may continue to retain
the amount of any retainage that was withheld from progress payments pursuant
to subsection 1.
3. If the contractor receives a payment of
interest earned on the retainage or an amount withheld from a progress payment,
the contractor shall, within 10 days after he or she receives the money, pay to
each subcontractor or supplier that portion of the interest received from the
public body which is attributable to the retainage or amount withheld from a
progress payment by the contractor to the subcontractor or supplier.
4. If, pursuant to subsection 3 of NRS 338.515 , the public body pays to the
contractor an amount of any retainage that was withheld from progress payments
pursuant to subsection 1 of NRS 338.515 for the portion of the work which has been performed by the subcontractor, the
contractor must pay to the subcontractor the portion of any retainage withheld
by the contractor pursuant to this section for the portion of the work.