Nevada Code § 338.16935

Contract between construction manager at risk and subcontractor for certain preconstruction services
Open in Lexace · Ask the AI about this section
1. Notwithstanding the provisions of NRS 338.16991 and 338.16995 , and subject to the provisions
of subsection 2, if a public body enters into a contract with a construction
manager at risk for preconstruction services pursuant to NRS 338.1693 , the construction manager at
risk may enter into a contract with a subcontractor licensed pursuant to chapter 624 of NRS to provide any of the
following preconstruction services, the basis of payment for which is a
negotiated price:
(a) Assisting the construction manager at risk in
identifying and selecting materials and equipment to be provided by each
subcontractor;
(b) Assisting the construction manager at risk in
creating a schedule for the provision of labor, materials or equipment by each
subcontractor;
(c) For the purpose of enabling the construction
manager at risk to establish a budget for the construction of the public work,
estimating the cost of labor, materials or equipment to be provided by each
subcontractor; and
(d) Providing recommendations to the construction
manager at risk regarding the design for the public work, as the design pertains
to the labor, materials or equipment to be provided by each subcontractor.
2. A subcontractor may not provide
preconstruction services pursuant to this section in an area of work outside
the field or scope of the license of the subcontractor.