Nevada Code § 338.141

Bids to include certain information concerning subcontractors and prime contractors; when bids deemed not responsive with respect to subcontractors; requirements and penalties for substitution of named subcontractors
Open in Lexace · Ask the AI about this section
1. Except as otherwise provided in NRS 338.1727 , each bid submitted to a
public body for any public work to which paragraph (a) of subsection 1 of NRS 338.1385 , paragraph (a) of subsection
1 of NRS 338.143 or NRS 408.327 applies, must include:
(a) If the public body provides a list of the
labor or portions of the public work which are estimated by the public body to
exceed 3 percent of the estimated cost of the public work, the name of each
first tier subcontractor who will provide such labor or portion of the work on
the public work which is estimated to exceed 3 percent of the estimated cost of
the public work; or
(b) If the public body does not provide a list of
the labor or portions of the public work which are estimated by the public body
to exceed 3 percent of the estimated cost of the public work, the name of each
first tier subcontractor who will provide labor or a portion of the work on the
public work to the prime contractor for which the first tier subcontractor will
be paid an amount exceeding 5 percent of the prime contractors total bid. If
the bid is submitted pursuant to this paragraph, within 2 hours after the
completion of the opening of the bids, the contractors who submitted the three
lowest bids must submit a list containing:
(1) The name of each first tier
subcontractor who will provide labor or a portion of the work on the public
work to the prime contractor for which the first tier subcontractor will be
paid an amount exceeding $250,000.
(2) If any one of the contractors who
submitted one of the three lowest bids will employ a first tier subcontractor
who will provide labor or a portion of the work on the public work to the prime
contractor for which the first tier subcontractor will not be paid an amount
exceeding $250,000, the name of each first tier subcontractor who will provide
labor or a portion of the work on the public work to the prime contractor for
which the first tier subcontractor will be paid 1 percent of the prime
contractors total bid or $50,000, whichever is greater.
(3) For each first tier subcontractor
whose name is listed pursuant to subparagraph (1) or (2), the number of the
license issued to the first tier subcontractor pursuant to chapter 624 of NRS.
2. The lists required by subsection 1 must
include a description of the labor or portion of the work which each first tier
subcontractor named in the list will provide to the prime contractor.
3. A prime contractor shall include his or
her name on a list required by paragraph (a) or (b) of subsection 1. If the
prime contractor will perform any work which is more than 1 percent of
the prime contractors total bid and which is not being performed by a
subcontractor listed pursuant to paragraph (a) or (b) of subsection 1, the
prime contractor shall also include on the list:
(a) A description of the labor or portion of the
work that the prime contractor will perform; or
(b) A statement that the prime contractor will
perform all work other than that being performed by a subcontractor listed
pursuant to paragraph (a) or (b) of subsection 1.
4. Except as otherwise provided in this
subsection, if a contractor:
(a) Fails to submit the list within the required
time; or
(b) Submits a list that includes the name of a
subcontractor who, at the time of the submission of the list, is on
disqualified status with the Division pursuant to NRS 338.1376 ,
the
contractors bid shall be deemed not responsive. A contractors bid shall not
be deemed not responsive on the grounds that the contractor submitted a list
that includes the name of a subcontractor who, at the time of the submission of
the list, is on disqualified status with the Division pursuant to NRS 338.1376 if the contractor, before the
award of the contract, provides an acceptable replacement subcontractor in the
manner set forth in subsection 1 or 2 of NRS
338.13895 .
5. A prime contractor shall not substitute
a subcontractor for any subcontractor who is named in the bid, unless:
(a) The public body or its authorized
representative objects to the subcontractor, requests in writing a change in
the subcontractor and pays any increase in costs resulting from the change.
(b) The substitution is approved by the public
body or its authorized representative. The substitution must be approved if the
public body or its authorized representative determines that:
(1) The named subcontractor, after having
a reasonable opportunity, fails or refuses to execute a written contract with
the contractor which was offered to the named subcontractor with the same
general terms that all other subcontractors on the project were offered;
(2) The named subcontractor files for
bankruptcy or becomes insolvent;
(3) The named subcontractor fails or
refuses to perform his or her subcontract within a reasonable time or is unable
to furnish a performance bond and payment bond pursuant to NRS 339.025 ; or
(4) The named subcontractor is not
properly licensed to provide that labor or portion of the work.
(c) If the public body awarding the contract is a
governing body, the public body or its authorized representative, in awarding
the contract pursuant to NRS 338.1375 to 338.139 , inclusive:
(1) Applies such criteria set forth in NRS 338.1377 as are appropriate for
subcontractors and determines that the subcontractor does not meet that
criteria; and
(2) Requests in writing a substitution of
the subcontractor.
6. If a prime contractor substitutes a
subcontractor for any subcontractor who is named in the bid without complying
with the provisions of subsection 5, the prime contractor shall forfeit, as a
penalty to the public body that awarded the contract, an amount equal to 1
percent of the total amount of the contract.
7. If a prime contractor, after the
submission of the bid, substitutes a subcontractor to perform the work
indicated pursuant to subsection 3 that the prime contractor would perform, the
prime contractor shall forfeit as a penalty to the public body that awarded the
contract, the lesser of, and excluding any amount of the contract that is
attributable to change orders:
(a) An amount equal to 2.5 percent of the total
amount of the contract; or
(b) An amount equal to 35 percent of the estimate
by the engineer of the cost of the work the prime contractor indicated pursuant
to subsection 3 that he or she would perform on the public work.
8. As used in this section:
(a) First tier subcontractor means a
subcontractor who contracts directly with a prime contractor to provide labor,
materials or services for a construction project.
(b) General terms means the terms and
conditions of a contract that set the basic requirements for a public work and
apply without regard to the particular trade or specialty of a subcontractor,
but does not include any provision that controls or relates to the specific
portion of the public work that will be completed by a subcontractor,
including, without limitation, the materials to be used by the subcontractor or
other details of the work to be performed by the subcontractor.

‹ Prev All Nevada sections Next ›


Lexace provides legal information, not legal advice, and no attorney–client relationship is created. Statute text is provided for general information and may not reflect the most recent amendments; verify against the official state code.