Nevada Code § 278.26506

Petition for review of decision of planning commission or governing body by Public Utilities Commission of Nevada; judicial review; regulations
Open in Lexace · Ask the AI about this section
1. An applicant for the issuance of a
special use permit for the construction of any utility project or for the
construction of a renewable energy generation project with a nameplate capacity
of 10 megawatts or more who:
(a) Believes that the decision of the planning
commission or governing body to approve or deny the applicants application was
not timely; or
(b) Disagrees with any conditions imposed by the
special use permit issued by the planning commission or governing body,
may, in the
manner prescribed by the Public Utilities Commission of Nevada by regulation,
petition the Public Utilities Commission of Nevada to review the decision of
the planning commission or governing body.
2. A petition submitted to the Public
Utilities Commission of Nevada pursuant to this section must include:
(a) The name, mailing address and telephone
number of the petitioner;
(b) The name of the planning commission or
governing body to whom the petitioner applied for a special use permit;
(c) A statement of the decision of the planning
commission or governing body from which review is sought;
(d) A statement of the resolution sought by the
petitioner;
(e) A statement of the legal basis for the
resolution sought by the petitioner;
(f) A copy of the application and all supporting
documents submitted by the petitioner to the planning commission or governing
body;
(g) A copy of each document issued by the
planning commission or governing body relating to the application; and
(h) Any other information required by the Public
Utilities Commission of Nevada.
3. In any proceeding before the Public
Utilities Commission of Nevada concerning a petition submitted pursuant to this
section, the parties:
(a) Must include:
(1) The petitioner;
(2) The planning commission or governing
body whose decision is the subject of the petition; and
(3) The Regulatory Operations Staff of the
Public Utilities Commission of Nevada; and
(b) May include:
(1) The Bureau of Consumer Protection in
the Office of the Attorney General, upon the filing by the Bureau of Consumer
Protection of a notice to intervene; and
(2) Any other person or entity that
participated in any proceeding before the planning commission or governing body
relating to the application for the issuance of a special use permit, if the
person or entity petitions the Public Utilities Commission of Nevada for, and
is granted, leave to intervene.
4. Not later than 150 days after receiving
a petition to review the decision of a planning commission or governing body,
the Public Utilities Commission of Nevada shall issue an order:
(a) Approving the decision of the planning
commission or governing body;
(b) Directing the planning commission or
governing body to issue a special use permit with such terms and conditions as
the Public Utilities Commission of Nevada determines are reasonable; or
(c) Directing the planning commission or
governing body to modify the terms and conditions of a special use permit in
the manner prescribed by the Public Utilities Commission of Nevada.
5. An order issued by the Public Utilities
Commission of Nevada pursuant to this section is final for the purposes of
judicial review.
6. The Public Utilities Commission of
Nevada shall adopt such regulations as it determines necessary to carry out the
provisions of this section.

‹ Prev All Nevada sections Next ›