Montana Code § 28-2-2110

Limit On Retainage
Open in Lexace · Ask the AI about this section
28-2-2110 . Limit on retainage. (1) The maximum retainage applied to construction contracts subject to the provisions of this part may not exceed 5%. (2) The retainage percentage withheld by an owner, as provided in subsection (1), from a construction contractor is the maximum retainage that a construction contractor may withhold from a subcontractor. (3) Retainage must be released upon the final acceptance of each portion of work for which a separate price is stated in the construction contract.

‹ Prev All Montana sections Next ›


Lexace provides legal information, not legal advice, and no attorney–client relationship is created. Statute text is provided for general information and may not reflect the most recent amendments; verify against the official state code.