(a) Subject to subsection (b) of this section, the Commission shall, by order
or regulation and subject to reasonable cost limitations balanced with the public
interest:
(1) expand the EV Pilot Program to allow participating electric
companies to install EV charging stations in new and existing multifamily dwellings
in underserved communities; and
(2) terminate the EV Pilot Program expansion required under item
(1) of this section on December 31, 2025.
(b) The termination of the EV Pilot Program expansion required under
subsection (a) of this section may not be construed to:
(1) terminate an electric company's authority to operate EV charging
stations under a program approved by the Commission on or before March 1, 2023;
(2) limit an electric company's efforts to operate and maintain EV
charging stations installed under the EV Pilot Program; or

(3) impact the cost recovery by an investor-owned electric company
for the lifetime of an EV charging station installed under the EV Pilot Program.