Maryland Code § PU-7-1218

Section PU-7-1218
Open in Lexace · Ask the AI about this section
(a) If the Commission approves an application that demonstrates, based on
the criteria specified in § 7-1214 of this subtitle, positive net economic impacts and
environmental and health benefits to the State, the Commission shall issue an order
in compliance with § 7-1217 of this subtitle.
(b) The Commission may not issue an order to facilitate the financing of a
nuclear energy generation project unless the project is subject to a community benefit
agreement under § 7-1202 of this subtitle.