(a) The Commission shall submit a final report, including construction cost
figures, on completed major projects to the county executive and county council of
Montgomery County or Prince George's County.
(b) (1) When the Commission submits a Program under § 23-304 of this
subtitle, the Commission shall include a status report of all approved major projects
that have not been completed as of the date that the Program is submitted.

(2) The report shall:
(i) identify the major project;
(ii) specify the dates of approval of the major project;
(iii) indicate the current status of the major project, including
an estimate of the date of completion of construction;
(iv) indicate if the major project is the subject of a material
change and any amendment that is required under § 23-312 of this subtitle; and
(v) for an approved major project in Montgomery County,
indicate a change in the last estimated construction costs and a modification in
location, size, and length of a construction item.