(a) If, within 30 years after completion of a project, a property with respect
to which funds have been paid under this subtitle is sold or transferred to any person,
agency, or organization that would not qualify as an applicant under this subtitle, or
that is not approved as a transferee by the Board of Public Works, or if, within the
same period, the property ceases to be a "facility" as defined in this subtitle, then the
State may recover from either the transferor or transferee or, in the case of a property
that has ceased to be a "facility" as defined in this subtitle, from the owner, an amount
bearing the same ratio to the then-current value of so much of the property as
constituted an approved project as the amount of the State participation bore to the
total eligible cost of the approved project, together with all costs and reasonable
attorneys' fees incurred by the State in the recovery proceedings.
(b) (1) Before the State makes any funds available for an approved
project, the Department shall cause a notice of this right of recovery to be recorded in
the land records of the county or Baltimore City in which the property is located.
(2) The recording of the notice:
(i) Does not create any lien against the property; but
(ii) Shall constitute notice to any potential transferee,
potential transferor, potential creditor, or other interested party of the possibility
that the State may obtain a lien under this subtitle.
(c) (1) In the event of an alleged sale or transfer as described in
subsection (b) of this section, or in the event that a property is alleged to have ceased
to be a "facility" as defined in this subtitle, the Secretary of the Board of Public Works
may file, in the circuit court for the county or Baltimore City in which the property is
located, a claim under this subtitle (styled as a civil action against the owner of the
property and any other interested parties, including any transferor that the State
wishes to make a party), together with sworn affidavits stating facts on which the
allegations of default are based, as well as a detailed justification of the amount
claimed.
(2) If the circuit court determines from the State's initial filing that
there is probable cause to believe that a default has occurred, the court shall
authorize a temporary lien on the property, in the amount of the State's claim (plus
any additional amount estimated to be necessary to cover the costs and reasonable
attorneys' fees incurred by the State) or in other amounts as the court determines to
be reasonable, pending full determination of the State's claim.
(3) The temporary lien shall take effect on the date of the court's
authorization if the Secretary of the Board of Public Works records a notice of

temporary lien in the land records of the county or Baltimore City in which the
property is located within 10 days thereafter, otherwise, the temporary lien shall take
effect on the date a notice of temporary lien is recorded. While the temporary lien is
in effect, neither the owner nor any person who acquired an interest in the property
after the State first made funds available in connection with the property under this
subtitle, may take any action that would affect the title to the property or institute
any proceedings to enforce a security interest or other similar rights in the property,
without the prior written consent of the State.
(4) The owner of the property or any other interested party may
obtain release of this temporary lien at any time by filing with the court a bond
securing the payment in full of the State's claim and any additional amount necessary
to cover the costs and reasonable attorneys' fees incurred by the State. The owner or
other interested party may cause the release to be recorded in the land records.
(d) (1) Proceedings to determine the State's right to recover and the
amount of its recovery under this subtitle shall have priority over other civil
proceedings in the circuit courts.
(2) At the conclusion of full adversary proceedings on the issue of
default and on any disputes over the amount of the State's recovery, the circuit court
shall, if it finds that a default has occurred, issue a final judgment for the amount it
finds to be recoverable by the State. All parties involved in the default, including in
every case the owner of the property, shall be held jointly and severally liable to the
State for the amount of the judgment. This amount, if it remains unpaid after the
expiration of 30 days following the court's final order, shall be a lien on the property,
superior (except as the State may by written subordination agreement provide
otherwise) to the lien or other interest of any mortgagee, pledgee, purchaser, or
judgment creditor whose interest became perfected against third persons after the
State first made funds available in connection with the property under this subtitle.
(3) This lien takes effect on the 31st day following the court's final
order if the Secretary of the Board of Public Works records a notice of lien in the land
records of the county or Baltimore City in which the property is located on or before
the 41st day following the final order, otherwise, the lien takes effect on the date a
notice of lien is recorded. At the time this lien takes effect, any temporary lien then
in effect shall be automatically and fully released, and the recorded notice of this lien
shall constitute notice of the release of the temporary lien.
(4) This lien may be enforced and foreclosed in accordance with the
procedures prescribed in the Maryland Rules, except that neither the State nor any
agent appointed by the State to sell the property need file a bond.

(5) The owner or any other interested party may obtain release of
this lien at any time by paying to the State the full amount of the judgment rendered
by the circuit court, together with interest from the date of judgment. On payment in
full, the Secretary of the Board of Public Works shall cause a release to be recorded
in the land records.
(6) If the circuit court finds that there has been no default or if the
full amount of the court's judgment is paid to the State within 30 days after the court's
final order, any temporary lien then in effect shall be released immediately and the
Secretary of the Board of Public Works shall cause the release to be recorded in the
land records.
(e) (1) All funds recovered as a result of this right of recovery shall be
deposited in the Annuity Bond Fund and applied to the debt service requirements of
the State.
(2) The Board of Public Works may waive the State's right of recovery
if the Board determines that there is good cause for releasing the transferor,
transferee, or owner from this obligation.