(a) (1) The Department may seek an order from the circuit court for the
county in which the land or water resources is located authorizing the Department,
its agents, employees, or contractors to enter upon the property adversely affected by
past coal mining practices and any other property to have access to the affected
property and to do all things necessary or expedient to restore, reclaim, abate, control,
or prevent the adverse effects, if the Department makes a finding of fact that:
(i) Land or water resources have been adversely affected by
past coal mining practices;
(ii) The adverse effects are at a stage where, in the public
interest, action to restore, reclaim, abate, control, or prevent should be taken; and
(iii) The owners of the land or water resources where entry
must be made to restore, reclaim, abate, control, or prevent the adverse effects of past
coal mining practices:
1. Are not known, or not readily available; or
2. Will not give permission for the Department, its
agents, employees, or contractors to enter on the property to restore, reclaim, abate,
control, or prevent the adverse effects of past coal mining practices.
(2) The court shall consider whether the entry is a necessary exercise
of the police power for the protection of the public health, safety, and welfare, and the
actions of the Department under a court order shall not be construed as an act of
condemnation of or trespass on property. The money expended for the work and the
benefits accruing to any premises so entered shall be chargeable against the land and
shall mitigate or offset any claim in or any action brought by any owner of any interest

in the premises for any alleged damages by virtue of the entry. This provision is not
intended to create new rights of action or eliminate existing immunities.
(b) Within 6 months after completion of a project pursuant to this subtitle,
the Department shall itemize the moneys expended by the Department and file a
notarized statement prepared by an independent appraiser as to the increase in value
of the land attributable to the reclamation project with the clerk of the circuit court
for the county in which the affected land lies. The statement shall constitute a lien
upon the land for an amount equal to the increase in the value attributable to the
project; provided that, no lien shall be filed:
(1) If the owner of the surface rights acquired the property prior to
May 2, 1977, and neither consented to nor participated in nor exercised control over
the mining operation which necessitated the reclamation project;
(2) If the primary purpose of the reclamation project is to benefit the
health, safety, and environmental values of the general public;
(3) If the cost of filing the lien exceeds the increase in the fair market
value of the property as a result of the reclamation project; or
(4) If the reclamation project is necessitated by an unforeseen
occurrence and the project does not significantly increase the fair market value of the
property.
(c) The landowner may, within 60 days of the filing of the lien, petition the
circuit court to determine the increase in the market value of the land as a result of
the reclamation project.
(d) The lien provided in this section shall constitute a lien upon the said
land as of the date of the expenditure of the moneys and shall have priority as a lien
second only to the lien of real estate taxes imposed upon said land. All funds received
by the State pursuant to this section shall be credited to the Federal-State
Reclamation Fund.

‹ Prev All Maryland sections Next ›


Lexace provides legal information, not legal advice, and no attorney–client relationship is created. Statute text is provided for general information and may not reflect the most recent amendments; verify against the official state code.