No later than January 1, 2010, all electricity consumed in state-owned buildings must be supplied by renewable resources. For purposes of this section, "renewable resource" has the same meaning as in Title 35-A, section 3210, subsection 2, paragraph C. In purchasing electricity for state-owned buildings, the State may give preference to electricity generated by community-based renewable energy projects, as defined in Title 35-A, section 3602, subsection 1 and electricity generated by combined heat and power projects, as defined in Title 35-A, section 3622, subsection 1. [PL 2021, c. 604, §1 (AMD).]