1. Review and approval required. Except as provided in this section or by commission rule:
A. A structure or part of a structure may not be erected, changed, converted or wholly or partly
altered or enlarged in its use or structural form without a permit issued by the commission. Normal
maintenance or repair may be made to a structure or part of a structure without a permit issued by
the commission in locations other than areas of special flood hazard as defined in the commission's
rules; [PL 2009, c. 111, §2 (AMD).]
B. A person may not commence development of or construction on any lot, parcel or dwelling unit
within any subdivision or sell or offer for sale any interest in any lot, parcel or dwelling unit within
any subdivision without a permit issued by the commission; or [PL 1999, c. 333, §12 (RPR).]
C. A person may not commence any construction or operation of any development without a permit
issued by the commission. [PL 1999, c. 333, §12 (RPR).]
[PL 2009, c. 111, §2 (AMD).]
1-A. Exceptions. Except as provided in this section or by commission rule:
A. A permit is not required for the repair and maintenance of an existing road culvert or for the
replacement of an existing road culvert, including ancillary culverting activities such as excavation
and filling, as long as:
(1) Erosion control measures are taken to prevent sedimentation of the water;
(2) The road culvert does not block passage for fish in flowing water; and
(3) For replacements of existing road culverts crossing flowing water:
(a) The replacement culvert is designed, installed and maintained to match the natural
grade of the channel bed of the water to avoid drops or perching; and

(b) As site conditions allow, culverts that are not open bottomed are embedded in the
channel bed of the water a minimum of one foot or at least 25% of the culvert or other
structure's diameter, whichever is greater, except that a culvert does not have to be
embedded more than 2 feet.
For purposes of this paragraph, "repair and maintenance" includes, but is not limited to, the
riprapping of side slopes or culvert ends; removing debris and blockages within the culvert structure
and at its inlet and outlet; and installing or replacing culvert ends if less than 50% of the culvert
structure is being replaced; [PL 2021, c. 590, Pt. A, §1 (RPR).]
B. [PL 2025, c. 11, §3 (RP).]
B-1. [PL 2025, c. 11, §4 (RP).]
REVISOR'S NOTE: (Paragraph B-1 as enacted by PL 2011, c. 653, §2 and affected by §33 is
REALLOCATED TO TITLE 12, SECTION 685-B, SUBSECTION 1-A, PARAGRAPH B-2)
B-2. (REALLOCATED FROM T. 12, §685-B, sub-§1-A, ¶B-1) [PL 2025, c. 11, §5 (RP).]
C. A permit is not required for a minor campground in a management district; [PL 2025, c. 11,
§6 (AMD).]
D. A permit is not required for an offshore wind energy demonstration project approved by the
Department of Environmental Protection pursuant to Title 38, section 480-HH. Notice of the intent
to develop and a map indicating the location of the proposed development must be filed with the
commission prior to or concurrently with submission of an application to the Department of
Environmental Protection pursuant to Title 38, section 480-HH; [PL 2025, c. 11, §7 (AMD).]
E. A permit or other approval by the commission is not required for a hydropower project that uses
tidal or wave action as a source of electrical or mechanical power or is located partly within an
organized municipality and partly within an unorganized territory; [PL 2025, c. 11, §8 (AMD).]
F. Except for projects that are located in a planned subdistrict that was approved or accepted by
the commission for processing prior to September 1, 2012, a permit is not required for those aspects
of a project approved by the Department of Environmental Protection pursuant to Title 38, chapter
3, subchapter 1, article 5-A if the commission determines that the project is an allowed use within
the subdistrict or subdistricts for which it is proposed. Notice of the intent to develop and a map
indicating the location of the proposed development must be filed with the commission prior to or
concurrently with the submission of a development application to the Department of Environmental
Protection; [PL 2025, c. 11, §9 (NEW).]
G. Except for projects located in a planned subdistrict approved or accepted by the commission
for processing prior to September 1, 2012, a permit from the commission is not required for
development requiring a permit from the Department of Environmental Protection pursuant to:
(1) The site location of development law, Title 38, chapter 3, subchapter 1, article 6;
(2) The Maine Metallic Mineral Mining Act, Title 38, chapter 3, subchapter 1, article 9; and
(3) The Maine Hazardous Waste, Septage and Solid Waste Management Act, Title 38, chapter
13.
A person who qualifies for an exception under this paragraph by being required to submit a permit
application to the Department of Environmental Protection for a proposed development located
wholly or in part within the unorganized or deorganized areas of the State shall file a notice of the
intent to develop and a map indicating the location of the proposed development with the
commission prior to or concurrently with the submission of an application to the Department of
Environmental Protection.

The Department of Environmental Protection must receive certification from the commission that
the proposed development is an allowed use within the subdistrict or subdistricts for which it is
proposed and that the proposed development meets any land use standard established by the
commission that is not considered in the department's review before issuing a permit.
The commission may not certify that a proposed expedited wind energy development, as defined
in Title 35-A, section 3451, subsection 4, within the expedited permitting area, as defined in Title
35-A, section 3451, subsection 3, is an allowed use if a relevant petition is pending under Title
35-A, section 3453-A, subsection 1.
This subsection may not be construed as prohibiting the commission from enforcing the land use
standards certified to the Department of Environmental Protection under this paragraph; and [PL
2025, c. 11, §10 (NEW).]
H. A permit from the commission is not required for the repair or maintenance of county-owned
roads, bridges or culverts as long as the repair or maintenance is conducted in accordance with
commission standards that pertain to these activities. [PL 2025, c. 11, §11 (NEW).]
[PL 2025, c. 11, §§3-11 (AMD).]
1-B. Delegation to staff. The commission may establish standards by which authority may be
delegated to its staff, to approve with reasonable conditions or deny applications submitted. Any person
aggrieved by a decision of the staff has the right to a review of that decision by the commission. A
request for such a review must be made within 30 days of the staff decision.
[PL 1999, c. 333, §13 (NEW).]
1-C. Delegation to county. The commission may establish standards by which authority may be
delegated to a county, upon request of the county commissioners, to approve, approve with reasonable
conditions or deny applications to conduct specified activities requiring a permit and to enforce
compliance with the permit. Any person aggrieved by a decision of a county has the right to appeal that
decision to the commission. Such an appeal must be made within 30 days after the county decision.
[PL 2011, c. 682, §16 (NEW).]
2. Application for approval. The application forms for approval, as provided by the commission,
must be completed and signed by the applicant and must be accompanied by the following:
A. A plan of the proposed structure, subdivision or development showing the intended use of the
real estate, the proposed change, the details of the project and such other information as may be
required by the commission to determine conformance with applicable land use standards; [PL
1989, c. 681, §1 (AMD).]
B. The fee prescribed by the commission rules, that fee to be a minimum of $50 but no greater
than 1/4 of 1% of the total development costs. The fees apply to all amendments except for minor
changes to building permits. In addition to the fee paid in accordance with this paragraph, the
director of the Maine Land Use Planning Commission may assess a processing fee on applications
for extraordinary projects in accordance with section 685-F; [PL 2007, c. 114, §1 (AMD); PL
2011, c. 682, §38 (REV).]
C. [PL 1977, c. 564, §51 (RP).]
D. Evidence of sufficient right, title or interest in all of the property that is proposed for
development or use. For purposes of this subsection, the written permission of the record owner
or owners of flowed land is deemed sufficient right, title or interest to confer standing for
submission of a permit application, provided that the letter of permission specifically identifies the
activities being performed and the area that may be used for that purpose. The commission may
not refuse to accept, under this paragraph, a permit application for any prohibited activity if the
owner or lessee of land adjoining a great pond has made a diligent effort to locate the record owner

or owners of the flowed land in question and has been unable to do so; and [PL 1989, c. 681, §1
(AMD).]
E. For a new or expanded development requiring an annual supply of wood or wood-derived
materials in excess of 150,000 tons green weight, a wood supply plan for informational purposes
to the Maine Forest Service at the time of application. The wood supply plan must include, but is
not limited to, the following information:
(1) The expected operational life of the development;
(2) The projected annual wood consumption of wood mill residue, wood fiber and recycled
materials from forest products during the entire operational life of the development;
(3) The expected market area for wood supply necessary to supply the development; and
(4) Other relevant wood supply information. [PL 1989, c. 681, §1 (NEW).]
[PL 2007, c. 114, §1 (AMD); PL 2011, c. 682, §38 (REV).]
2-A. Priority for processing. Applications to replace destroyed seasonal or permanent structures
shall be given top priority for processing when hardship can be demonstrated by the applicant provided
that:
A. The dimensions of the new structure are not greater than the preexisting structure; and [PL
1989, c. 22, §1 (NEW).]
B. The new structure will not adversely affect surrounding uses and resources. [PL 1989, c. 22,
§1 (NEW).]
[PL 1989, c. 22, §1 (NEW).]
2-B. Determination deadline. The commission shall render its determination on an application
for subdivision approval within 60 days after the commission determines that the application is
complete and the proposal is a permitted use within the affected district or subdistrict.
[PL 1989, c. 584, §2 (NEW); PL 1989, c. 810, §2 (AMD).]
2-C. Wind energy development; community-based offshore wind energy projects;
determination deadline. For purposes of this subsection, "expedited permitting area," "grid-scale
wind energy development" and "wind energy development" have the same meanings as in Title 35-A,
section 3451. The following provisions govern wind energy development.
A. The commission shall consider any wind energy development in the expedited permitting area
under Title 35-A, chapter 34-A with a generating capacity of 100 kilowatts or greater or a
community-based offshore wind energy project a use requiring a permit, but not a special
exception, within the affected districts or subdistricts. [PL 2011, c. 682, §17 (RPR).]
B. All grid-scale wind energy development proposed for the unorganized or deorganized areas of
the State is reviewed and permits are issued by the Department of Environmental Protection under
Title 35-A, chapter 34-A and Title 38, section 489-A-1. [PL 2011, c. 682, §17 (RPR).]
C. For an offshore wind energy project that is proposed within one nautical mile of an island within
the unorganized or deorganized areas, the commission shall review the proposed project to
determine whether the project qualifies as a community-based offshore wind energy project and
therefore is within the jurisdiction of the commission. [PL 2011, c. 682, §17 (NEW).]
D. Except for a grid-scale wind energy project, the commission may require an applicant to provide
a timely notice of filing prior to filing an application for, and may require the applicant to attend a
public meeting during the review of, a wind energy development or a community-based offshore
wind energy project. For projects or development located within the expedited permitting areas,
the commission shall render its determination on an application for such a development or project
within 185 days after the commission determines that the application is complete, except that the

commission shall render such a decision within 270 days if it holds a hearing on the application.
The chair of the Public Utilities Commission or the chair's designee shall serve as a nonvoting
member of the commission and may participate fully but is not required to attend hearings when
the commission considers an application for a community-based offshore wind energy project. The
chair's participation on the commission pursuant to this subsection does not affect the ability of the
Public Utilities Commission to submit information into the record of the commission's proceedings.
[PL 2011, c. 682, §17 (NEW).]
E. At the request of an applicant, the commission may stop the processing time for a period of time
agreeable to the commission and the applicant. The expedited review period specified in paragraph
D does not apply to the associated facilities, as defined in Title 35-A, section 3451, subsection 1,
of the wind energy development or community-based offshore wind energy project if the
commission determines that an expedited review time is unreasonable due to the size, location,
potential impacts, multiple agency jurisdiction or complexity of that portion of the development or
project. [PL 2011, c. 682, §17 (NEW).]
[PL 2011, c. 682, §17 (RPR).]
2-D. Transmission line or lines under Northern Maine Renewable Energy Development
Program. A transmission line or lines developed under the Northern Maine Renewable Energy
Development Program pursuant to Title 35-A, section 3210-I, subsection 2 and proposed within
unorganized or deorganized areas of the State is reviewed and permits are issued by the Department of
Environmental Protection under Title 38, section 489-A-1.
[PL 2023, c. 660, §1 (NEW).]
3. Hearings and procedures.
[PL 1999, c. 333, §14 (RP).]
3-A. Hearings and procedures. Hearings and procedures in connection with the review and
approval of a permit application are subject to this subsection. To the extent practicable, hearings held
under this subsection must be held at a location in close proximity to the project or projects under
review.
A. The commission may determine on its own motion to hold a hearing on the application. [PL
1999, c. 333, §15 (NEW).]
B. If the commission determines to act upon a permit application without a hearing, the
commission, within 90 days after receiving the complete application, shall make findings of fact
and issue an order either granting approval, subject to reasonable terms and conditions that the
commission determines appropriate in order to fulfill the requirements and intent of this chapter,
the comprehensive land use plan and the commission's standards, or denying approval of the
application as proposed. [PL 1999, c. 333, §15 (NEW).]
C. Any person aggrieved by a decision of the commission or its staff concerning any permit
application upon which no hearing was held may, within 30 days of that decision, petition the
commission for a hearing. The commission is not required to hold a hearing, but shall respond
within 45 days of receipt of the petition by notifying the petitioner in writing of the date, time and
place set for the requested hearing or of the denial of the request. [PL 1999, c. 333, §15 (NEW).]
D. Within 60 days after the commission adjourns any hearing held under this subsection, it shall
make findings of fact and issue an order either granting approval, subject to reasonable terms and
conditions that the commission determines appropriate in order to fulfill the requirements and intent
of this chapter, the comprehensive land use plan and the commission's standards, or denying
approval of the application as proposed. [PL 1999, c. 333, §15 (NEW).]
[PL 2011, c. 682, §18 (AMD).]

4. Criteria for approval. In approving applications submitted to it pursuant to this section, the
commission may impose such reasonable terms and conditions as the commission may consider
appropriate. In making a decision under this subsection regarding an application for a community-
based offshore wind energy project, the commission may not consider whether the project meets the
specific criteria designated in section 1862, subsection 2, paragraph A, subparagraph (6), divisions (a)
to (d). This limitation is not intended to restrict the commission's review of related potential impacts
of the project as determined by the commission.
The commission may not approve an application, unless:
A. Adequate technical and financial provision has been made for complying with the requirements
of the State's air and water pollution control and other environmental laws, and those standards and
regulations adopted with respect thereto, including without limitation the minimum lot size laws,
sections 4807 to 4807-G, the site location of development laws, Title 38, sections 481 to 489-E,
and the natural resource protection laws, Title 38, sections 480-A to 480-Z, and adequate provision
has been made for solid waste and sewage disposal, for controlling of offensive odors and for the
securing and maintenance of sufficient healthful water supplies; [PL 2011, c. 653, §3 (AMD);
PL 2011, c. 653, §33 (AFF).]
B. Adequate provision has been made for loading, parking and circulation of land, air and water
traffic in, on and from the site, and for assurance that the proposal will not cause congestion or
unsafe conditions with respect to existing or proposed transportation arteries or methods; [PL
2011, c. 682, §19 (AMD).]
C. Adequate provision has been made for fitting the proposal harmoniously into the existing natural
environment in order to ensure there will be no undue adverse effect on existing uses, scenic
character and natural and historic resources in the area likely to be affected by the proposal.
(1) In making a determination under this paragraph regarding whether an applicant has made
adequate provision for fitting the proposal harmoniously into the existing natural environment,
the commission may consider the effect of at least 1.5 feet of sea level rise by 2050 and 4 feet
of relative sea level rise by 2100 as specified by the commission by rule adopted pursuant to
section 685-A, subsection 3.
(2) In making a determination under this paragraph regarding development to facilitate
withdrawal of groundwater, the commission shall consider the effects of the proposed
withdrawal on waters of the State, as defined by Title 38, section 361-A, subsection 7; water-
related natural resources; and existing uses, including, but not limited to, public or private
wells, within the anticipated zone of contribution to the withdrawal. In making findings under
this subparagraph, the commission shall consider both the direct effects of the proposed
withdrawal and its effects in combination with existing water withdrawals.
(3) In making a determination under this paragraph regarding a community-based offshore
wind energy project, the commission shall consider the project's effects on scenic character and
existing uses related to scenic character in accordance with Title 35-A, section 3452.
(4) In making a determination under this paragraph regarding a wind energy development, as
defined in Title 35-A, section 3451, subsection 11, that is not a grid-scale wind energy
development, that has a generating capacity of 100 kilowatts or greater and that is proposed for
location within the expedited permitting area, the commission shall consider the development's
or project's effects on scenic character and existing uses relating to scenic character in the
manner provided for in Title 35-A, section 3452; [PL 2021, c. 590, Pt. A, §2 (RPR).]
C-1. With respect to a wind energy development that has a generating capacity of 100 kilowatts or
greater, the person proposing the development has received certification from the Department of

Environmental Protection in the manner provided under Title 35-A, section 3456; [PL 2011, c.
682, §19 (NEW).]
D. The proposal will not cause unreasonable soil erosion or reduction in the capacity of the land
to absorb and hold water and suitable soils are available for a sewage disposal system if sewage is
to be disposed on-site; [PL 1999, c. 333, §17 (AMD).]
E. The proposal is otherwise in conformance with this chapter and the regulations, standards and
plans adopted pursuant thereto; and [PL 2007, c. 661, Pt. C, §3 (AMD).]
F. In the case of an application for a structure upon any lot in a subdivision, that the subdivision
has received the approval of the commission. [PL 1973, c. 569, §11 (NEW).]
The burden is upon the applicant to demonstrate by substantial evidence that the criteria for approval
are satisfied, and that the public's health, safety and general welfare will be adequately protected. The
commission shall permit the applicant and other parties to provide evidence on the economic benefits
of the proposal as well as the impact of the proposal on energy resources.
[PL 2021, c. 590, Pt. A, §2 (AMD).]
4-A. Subdivision of land subject to liquidation harvesting. The commission may not approve
an application for a subdivision if the commission determines that timber on the parcel proposed for
subdivision has been harvested in violation of rules adopted pursuant to section 8869, subsection 14.
If a violation of rules adopted by the Maine Forest Service to substantially eliminate liquidation
harvesting has occurred, the commission must determine prior to granting approval for the subdivision
that 5 years have elapsed from the date the landowner under whose ownership the harvest occurred
acquired the parcel. The commission may request technical assistance from the Maine Forest Service
to determine if a rule violation has occurred.
For the purposes of this subsection, "liquidation harvesting" has the same meaning as in section 8868,
subsection 6 and "parcel" means a contiguous area within one municipality, township or plantation
owned by one person or a group of persons in common or joint ownership. This subsection takes effect
on the effective date of rules adopted pursuant to section 8869, subsection 14.
[PL 2003, c. 622, §1 (NEW).]
4-B. Special provisions; community-based offshore wind energy project. In the case of a
community-based offshore wind energy project, the developer must demonstrate, in addition to
requirements under subsection 4, that the proposed generating facilities, as defined in Title 35-A,
section 3451, subsection 5:
A. Will meet the requirements of the Board of Environmental Protection's noise control rules
adopted pursuant to Title 38, chapter 3, subchapter 1, article 6; [PL 2007, c. 661, Pt. C, §4
(NEW).]
B. Will be designed and sited to avoid undue adverse shadow flicker effects; and [PL 2011, c.
682, §20 (AMD).]
C. Will be constructed with setbacks adequate to protect public safety, as provided in Title 35-A,
section 3455. In making findings pursuant to this paragraph, the commission shall consider the
recommendation of a professional, licensed civil engineer as well as any applicable setback
recommended by a manufacturer of the generating facilities. [PL 2011, c. 682, §20 (AMD).]
D. [PL 2011, c. 682, §20 (RP).]
[PL 2011, c. 682, §20 (AMD).]
5. Limitation, expiration, transfer and revocation of approval. Commission authorization
pursuant to this section shall permit only the arrangement and construction set forth in the approval as
issued. Change in use, arrangement or construction shall be considered a violation of this chapter and
punishable as provided in this chapter.

A violation of any condition attached to a commission approval or permit, or any change in use,
arrangement or construction from that approved, shall be deemed a violation of this chapter and, in
addition to any other penalties or remedies prescribed herein or otherwise provided by law, shall
constitute grounds for the revocation or suspension of this approval. The commission may, acting in
accordance with Title 5, section 10003, amend, modify or refuse to renew any commission approval or
permit where the commission determines that the criteria for approval set forth in subsection 4,
paragraphs A to F, have not been, are not being, or will not be satisfied.
[PL 1977, c. 694, §232 (AMD).]
6. Recording of approved proposals. A copy of each application, marked approved or
disapproved, shall be retained in the commission files and shall be available to the public during normal
business hours.
In the event the commission approves an application for subdivision approval, a copy of an approved
plat or plan and a copy of the conditions required by the commission to be set forth in any instrument
conveying an interest within the subdivision attested to by an authorized commission signature shall be
filed with the appropriate registry of deeds in the county in which the real estate lies.
A registrar of deeds shall not record a copy of conditions or any plat or plan purporting to subdivide
real estate located within the unorganized and deorganized lands of the State, unless the commission's
approval is evidenced thereon.
The grantee of any conveyance of unrecorded subdivided real estate or subdivided real estate recorded
in violation of this section may recover the purchase price, at interest, together with damages and costs
in addition to any other remedy provided by law.
[PL 1987, c. 885, §5 (AMD).]
6-A. Recording of land division plan required. A copy of each land division plan must be
recorded in the registry of deeds of the county in which the land is located.
A. When 3 to 10 lots each containing at least 40 acres are created within a 5-year period and are
located more than 1,320 feet from the normal high water line of any great pond or river and more
than 250 feet from the upland edge of a coastal or freshwater wetland as defined in Title 38, section
436-A, a plan showing the division of the original parcel must be filed by the person creating the
3rd lot with the commission within 60 days of the creation of that lot. The plan must state that the
lots may be used only for forest management, agricultural management or conservation of natural
resources. [PL 2001, c. 431, §4 (AMD).]
B. A register of deeds may not record any plan depicting these lots within the unorganized and
deorganized lands of the State unless the commission's certification that the division qualifies under
section 682-B is evidenced on the plan. The commission must determine whether the plan qualifies
under section 682-B within 15 business days of receipt of the plan. [PL 2001, c. 431, §4 (AMD).]
C. A copy of the certified plan must be filed within 30 days of certification with the State Tax
Assessor and the appropriate registry of deeds in the county in which the land is located. [PL 1991,
c. 687, §2 (NEW).]
D. Failure to file the plan required by this subsection is a violation of this chapter subject to the
penalties provided in section 685-C, subsection 8. [PL 1991, c. 687, §2 (NEW).]
[PL 2001, c. 431, §4 (AMD).]
6-B. Notification of land division required.
[PL 2001, c. 431, §5 (RP).]
7. Nonconforming uses and nonconforming structures. To achieve the purposes set forth in
this chapter after the adoption of permanent district standards and permanent districts, the commission

may regulate and prohibit expansion and undue perpetuation of nonconforming uses. Specifically the
commission may regulate and prohibit:
A. Changes in nonconforming uses to another nonconforming use; [PL 1971, c. 457, §5 (NEW).]
B. Extension or enlargement of nonconforming uses or nonconforming structures; [PL 1989, c.
22, §2 (AMD).]
C. Resumption of nonconforming uses, by prohibiting such resumption if such use is discontinued
for 2 years or abandoned; and [PL 1973, c. 569, §11 (AMD).]
D. Movement or enlargement of a nonconforming structure or of a structure containing a
nonconforming use. [PL 1971, c. 457, §5 (NEW).]
The commission may also provide for the termination of commercial or industrial nonconforming uses
by specifying in land use standards the period or periods in which nonconforming uses shall be
terminated and by adjusting such compulsory terminations so as to allow reasonable time for the
conversion of such nonconforming uses and reasonable schedules for the amortization of investment.
Any use for which a special exception has been granted by the commission, as provided for in section
685-A, subsection 10, shall not be deemed a nonconforming use, but shall be deemed a conforming use
in such district.
For applications to reconstruct a damaged or destroyed nonconforming structure, the commission shall
require the new structure to comply with provisions of this chapter to the maximum extent possible.
[PL 1989, c. 22, §2 (AMD).]
7-A. Reconstruction of commercial sporting camps. The commission may approve a permit for
the reconstruction of a damaged or destroyed nonconforming commercial sporting camp that was a
permissible use under commission standards at the time of the damage or destruction. The commission
may, consistent with public health, safety and welfare, and to the minimum extent necessary, waive
standards that made the original structure nonconforming. The reconstructed structure must replicate
the original structure and use to the maximum extent possible and it must be on the same location and
within the same footprint as the original structure. Reconstruction must occur within 2 years of the
damage or destruction.
[PL 1995, c. 386, §3 (NEW).]
7-B. Presumption of nonconforming uses and nonconforming structures. If a person
demonstrates that a use or structure that does not conform with district standards has existed for at least
30 years, there is a rebuttable presumption that the use is a nonconforming use or that the structure is a
nonconforming structure.
[PL 2017, c. 89, §1 (NEW).]
8. Certificates of compliance. It shall be unlawful to use or occupy or permit the use or occupancy
of any land, structure, or part thereof, created, erected, changed, converted, or wholly or partly altered
or enlarged in its use or structural form, requiring subsequent review and approval pursuant to this
subchapter, until a certificate of compliance has been issued therefor by the commission stating that the
requirements and conditions of approval have been met.
A certificate of compliance may contain such terms and conditions as will protect the health, safety and
general welfare of the occupants, users and the public.
The commission may establish standards within which authority shall be delegated to its staff, to issue
or deny certificates of compliance. Any person aggrieved by a decision of the staff shall have the right
to a review of such decision by the commission members within 30 days of such decision.
[PL 1973, c. 569, §11 (AMD).]
9. Periodic review of district boundaries and land use standards.
[PL 1973, c. 569, §12 (RP).]

10. Moratorium. The commission may adopt a moratorium on the processing or issuance of
development permits on a township-by-township basis, on portions of a township or on portions of the
territory under its jurisdiction. Any moratorium adopted by the commission must meet the following
requirements.
A. The moratorium must be necessary:
(1) To prevent the shortage or overburdening of public facilities which would otherwise occur
during the effective period of the moratorium or which is reasonably foreseeable as a result of
any proposed or anticipated development; or
(2) Because the application of existing comprehensive plans, land use or zoning regulations or
other applicable laws, if any, is inadequate to prevent serious public harm from residential,
commercial or industrial development in the affected geographic area. [PL 1989, c. 47, §2
(NEW).]
B. The moratorium must be of a definite term not to exceed 180 days except that the moratorium
may be extended for additional 180-day periods provided that the commission:
(1) Finds that the problem creating the need for a moratorium still exists; and
(2) Finds that reasonable progress is being made to alleviate the problem creating the need for
a moratorium. [PL 1989, c. 47, §2 (NEW).]
C. Any organized town or plantation which has petitioned the commission to remove that town or
plantation from the jurisdiction of the Maine Land Use Planning Commission in compliance with
section 685-A, subsection 4, may, through a town meeting, vote to adopt a moratorium to provide
a period of time for the town or plantation to adopt a local comprehensive plan and zoning
ordinance and to establish a municipal reviewing authority. The moratorium must be in compliance
with paragraphs A and B. The municipal officers, acting in place of the commission, may extend
the moratorium pursuant to paragraph B after notice and hearing. [PL 1989, c. 47, §2 (NEW);
PL 2011, c. 682, §38 (REV).]
[PL 1989, c. 47, §2 (NEW); PL 2011, c. 682, §38 (REV).]

‹ Prev All Maine sections Next ›


Lexace provides legal information, not legal advice, and no attorney–client relationship is created. Statute text is provided for general information and may not reflect the most recent amendments; verify against the official state code.