Sec. 10. (a) The board may grant an applicant's request for preconstruction project planning design and development costs. (b) A request submitted under subsection (a) must be in writing. (c) The board may not grant a request under subsection (a) if the total design and development expenditure exceeds fifteen percent (15%) of the total construction costs for the project. (d) The board shall require adequate documentation of eligible costs before approving reimbursement under this section.