Indiana Code § 8-23-1-40.5

"Substantial completion"
Open in Lexace · Ask the AI about this section
Sec. 40.5. "Substantial completion" refers to the date, as determined by the department, when the construction of the contract is sufficiently completed in accordance with the plans and specifications, as modified by any change orders, so that the construction can be used for its intended purpose.