Sec. 9. (a) Unless and until a proposal is accepted, the drawings, specifications, and other information in the proposal are the property of the offeror. (b) After a proposal is accepted, ownership of the drawings, specifications, and information in the drawings and specifications shall be determined under Indiana law and the terms of the design-build contract. IC 5-30-8 Chapter 8. Miscellaneous Provisions 5-30-8-0.1 Application of certain amendments to chapter 5-30-8-1 Changes in public project; validity of design-build contract 5-30-8-2 Replacement of subcontractor for primary design services and construction services 5-30-8-3 Adjustment of maximum cost by agreement 5-30-8-4 Performance and payment bonds required 5-30-8-5 Certain acts by public agency prohibited 5-30-8-6 Repealed 5-30-8-7 Repealed