Indiana Code § 5-16-13-9

Tier 1 contractor required work, materials, or services contribution to public works contract
Open in Lexace · Ask the AI about this section
Sec. 9. Each tier 1 contractor must contribute in: (1) work performed by the tier 1 contractor's employees; (2) materials supplied directly by the tier 1 contractor; (3) services supplied directly by the tier 1 contractor's employees; or (4) any combination of subdivisions (1) through (3); at least fifteen percent (15%) of the tier 1 contractor's total contract price as determined at the time the contract is awarded.

‹ Prev All Indiana sections Next ›


Lexace provides legal information, not legal advice, and no attorney–client relationship is created. Statute text is provided for general information and may not reflect the most recent amendments; verify against the official state code.