Sec. 1. (a) A person may not after June 30, 2011, start: (1) construction of: (A) a biomass anaerobic digestion facility; or (B) a biomass gasification facility; or (2) expansion of: (A) a biomass anaerobic digestion facility; or (B) a biomass gasification facility; without obtaining prior approval of the department. (b) A person who proposes to construct or expand a biomass anaerobic digestion facility or a biomass gasification facility on the premises of a confined feeding operation must obtain the prior approval required under subsection (a) through the approval process for confined feeding operations under IC 13-18-10 and rules implementing that chapter.