Illinois Code § 770 ILCS 60/6

In no event shall it be necessary to fix or stipulate in any
Open in Lexace · Ask the AI about this section
contract a time for the completion or a time for payment in order to obtain
a lien under this Act, provided, that the work is done or material
furnished within three years from the commencement of said work or the
commencement of furnishing said material in the case of work done or material furnished as to residential property; and within 5 years from the commencement of said work or the commencement of furnishing said material in the case of work done or material furnished as to any other type of property. The changes made by Public Act 97-966 are operative from January 1, 2013 through December 31, 2024.