Illinois Code § 70 ILCS 2805/84

Completing unfinished work and
Open in Lexace · Ask the AI about this section
contractor's bond. Except as otherwise provided in Section
9-2-113 of the Illinois Municipal Code, as now or hereafter amended, if the
contractors who may have taken any contract do not complete the work
within the time mentioned in the contract or within such
further time as the committee may give them, the committee
may relet the unfinished portions of that work after
pursuing the bidding formalities prescribed in this Act for
the letting of the whole in the first instance.

 
All contractors at the time of executing any contract
for such unfinished work shall execute a bond as provided
for in Section 81 of this Act.