Illinois Code § 70 ILCS 1505/26.10-6

Solicitation of design-build proposals.
Open in Lexace · Ask the AI about this section
(a) When the Chicago Park District elects to use the design-build delivery
method, it must
issue a notice of intent to receive proposals for the project at
least 14 days before issuing the request for the proposal. The Chicago Park District
must publish the advance notice in a daily newspaper of general circulation in Cook County. The
Chicago Park District is encouraged to use publication of the notice in related construction
industry service publications. A brief description of the proposed procurement
must be included in the notice. The Chicago Park District must provide a
copy of the
request for proposal to any party requesting a copy.
 
(b) The request for proposal shall be prepared for each project and must
contain, without limitation, the following information:
 
 
(1) A preliminary schedule for the completion of the 
 
contract. 

 
 
(2) The proposed budget for the project, the source 
 
of funds, and the currently available funds at the time the request for proposal is submitted. 

 
 
(3) Prequalification criteria for design-build 
 
entities wishing to submit proposals. The Chicago Park District shall include, at a minimum, its normal prequalification, licensing, registration, and other requirements, but nothing contained herein precludes the use of additional prequalification criteria by the Chicago Park District. 

 
 
(4) Material requirements of the contract, including 
 
but not limited to, the proposed terms and conditions, required performance and payment bonds, insurance, and the entity's plan to comply with the utilization goals established by the corporate authorities of the Chicago Park District for minority and women business enterprises and to comply with Section 2-105 of the Illinois Human Rights Act. 

 
 
(5) The performance criteria.

 
 
(6) The evaluation criteria for each phase of the 
 
solicitation. 

 
 
(7) The number of entities that will be considered 
 
for the technical and cost evaluation phase. 
 
(c) The Chicago Park District may include any other relevant information
that it
chooses to supply. The design-build entity shall be entitled to rely upon the
accuracy of this documentation in the development of its proposal. 
 
(d) The date that proposals are due must be at least 21 calendar days after
the date of the issuance of the request for proposal. In the event the cost of
the project
is estimated to exceed $12,000,000, then the proposal due date must be at least
28 calendar days after the date of the issuance of the request for proposal.
The Chicago Park District shall include in the request for proposal a
minimum of 30 days
to develop the Phase II submissions after the selection of entities
from the Phase I evaluation is completed. 

contract.
of funds, and the currently available funds at the time the request for proposal is submitted.
entities wishing to submit proposals. The Chicago Park District shall include, at a minimum, its normal prequalification, licensing, registration, and other requirements, but nothing contained herein precludes the use of additional prequalification criteria by the Chicago Park District.
but not limited to, the proposed terms and conditions, required performance and payment bonds, insurance, and the entity's plan to comply with the utilization goals established by the corporate authorities of the Chicago Park District for minority and women business enterprises and to comply with Section 2-105 of the Illinois Human Rights Act.
solicitation.
for the technical and cost evaluation phase.