Delaware Code § 7-4013

Approval of certified construction reviewers
Open in Lexace · Ask the AI about this section
(a) Based on criteria established by the Department through regulation and any additional criteria established by the agency
implementing the plan review and construction elements of the sediment and stormwater program, the person engaged in a land disturbing
activity may be required to provide for construction review by a certified construction reviewer.
(b) Individuals functioning as certified construction reviewers must attend and pass a departmental sponsored or approved construction
review training course. The Department will establish, through regulation, the length of time for which the certification will last and
procedure for renewal. The construction reviewers shall also function under the direction of a registered professional engineer licensed
to practice engineering in the State.
(c) The responsibility of the certified construction reviewer will be to ensure the adequacy of construction pursuant to the approved
sediment and stormwater management plan.
(d) The certified construction reviewer shall be responsible for the following items:
(1) Provision of a construction review of active construction sites on at least a weekly basis, as determined on a case-by-case basis
by the plan review and construction review agencies, or as required by regulations promulgated pursuant to this chapter;
(2) Within 5 calendar days, informing the person engaged in the land disturbing activity, and the contractor, by a written construction
review report of any violations of the approved plan or inadequacies of the plan. The plan approval agency shall be informed, if the
approved plan is inadequate, within 5 working days. In addition, the appropriate construction review agency shall receive copies of
all construction review reports; and

(3) Referral of the project to the Department for appropriate enforcement action if the person engaged in the land disturbing activity
fails to address the items contained in the written construction review report. Verbal notice shall be made to the Department within 2
working days and written notice shall be provided to the Department within 5 working days.
(e) If the Secretary or the Secretary's designee determines that a certified construction reviewer is not providing adequate site control
or is not referring problem situations to the Department, the Secretary or the Secretary's designee may suspend or revoke the certification
of the construction reviewer.
(f) In any situation where a certified construction reviewer's approval is being suspended or revoked, an opportunity for hearing before
the Secretary or the Secretary's designee shall be provided. During any suspension or revocation, the certified construction reviewer shall
not be allowed to provide construction reviews pursuant to this chapter.
(g) The failure to assign a departmental approved certified construction reviewer to a land disturbing activity, when required by the
approved plan, will place that project in violation of this chapter and result in appropriate administrative and/or enforcement action.