44, § 2]. No county shall deny a conditional use permit to any electrical substation, along with any directly related project infrastructure, proposed to be located on unincorporated land within such county where the following conditions apply: (1) The substation is being proposed to support the operation of a proposed renewable energy generation project of 250 MW or greater; (2) The proposed substation would be located in a heavy industrial zone; (3) An electrical substation is an allowed conditional use within the proposed zone; and (4) The specific zoning district in which the proposed substation would be located already has an electric substation located in such zone with a rating of 230kv or greater as of August 3, 2023. Caller Identification Service