Colorado Code § 43-1-1406

General procedures
Open in Lexace · Ask the AI about this section
(1) The department shall describe in the specifications
for the transportation project the particular design-build contract and selection procedures to be
used in awarding such contract, including but are not limited to the following:
(a) A scope of work statement that defines the transportation project and provides
prospective design-build firms with sufficient information regarding the department's
requirements for the transportation project;
(b) If the department uses an adjusted score design-build contract process to select a
design-build firm, a scope of work statement that is flexible and that identifies the end result that
the department wants to achieve. The department may determine the adjustment factors and
methods it will use to adjust scores and shall state such factors and methods in the specifications
for the transportation project. The department may also provide a general concept of the
transportation project to potential design-build firms. Adjusted score design-build procedures
shall consist of the following two phases:
(I) In the first phase, the department shall issue a request for qualifications within the
time specified in section 43-1-1405 to solicit proposals that include information on the design-
build firm's qualifications and its technical approach to the proposed transportation project. The
department shall include appropriate evaluation factors in the request for qualifications,
including the factors set forth in section 24-30-1403 (2), C.R.S. The department shall not include
cost-related or price-related factors in the request for qualifications. In accordance with the time
requirements specified in the department's rules, the department shall develop a short list of the
highest qualified design-build firms from the proposals submitted in response to the request for
qualifications.
(II) In the second phase, the department shall issue a request for proposals to the design-
build firms included on the short list developed pursuant to subparagraph (I) of this paragraph
(b) in accordance with the time requirements specified in the department's rules. The request for
proposals shall include:
(A) A request to separately submit a sealed technical proposal and a sealed cost proposal
for the transportation project;
(B) The required content of the technical proposal to be submitted by the design-build
firm, including design concepts for the transportation project, the proposed solutions to the
requirements addressed in the department's scope of work statement, or both;
(C) Any other evaluation factors the department considers appropriate, including the
estimated cost of the transportation project; and
(D) Any formula the department determines is appropriate to adjust the total score of a
design-build firm's proposal.
(2) Except as provided in this subsection (2), the department shall allow the preference
to Colorado residents provided in section 24-103-908 in awarding an adjusted score design-build
contract pursuant to this part 14. In evaluating and selecting a proposal for a design-build
contract under this part 14, the department shall assign greater value to a proposal in proportion
to the extent such proposal commits to using Colorado residents to perform work on the
transportation project. If, however, the department determines that compliance with this
subsection (2) may cause the denial of federal moneys that would otherwise be available for the
transportation project or if such compliance would otherwise be inconsistent with the
requirements of federal law, the department shall suspend the preference granted under this
subsection (2) only to the extent necessary to prevent denial of federal moneys or to eliminate
the inconsistency with federal law.
(3) The department may use any basis for awarding a design-build contract pursuant to
this part 14 that it deems appropriate so long as the basis for awarding such contract is
adequately described in the specifications for the transportation project or the request for
proposals. Such basis may include awarding a contract to the design-build firm whose proposal
provides the best value to the department.
(4) The department may cancel any request for qualifications, request for proposals, or
other solicitation issued pursuant to this part 14 or may reject any or all proposals in whole or in
part when the department determines that such cancellation or rejection is in the best interest of
the department.
(5) If the department awards a design-build contract pursuant to this part 14, the
department shall execute a design-build contract with the successful design-build firm and shall
give notice to said firm to commence work on the transportation project.