Colorado Code § 33-5-104

Notice by commission. Within thirty days after the receipt of any plans
Open in Lexace · Ask the AI about this section
submitted to it, the commission shall notify the applicant if the planned construction or project
will adversely affect the stream involved. If an applicant is notified that the planned construction
will adversely affect any stream involved, the commission shall accompany such notice with
recommendations or alternative plans which will eliminate or diminish such adverse effect.