Colorado Code § 32-11-617

Extra work authorized - payment. Extra work may arise in connection
Open in Lexace · Ask the AI about this section
with any project mentioned in this article and not particularly provided for in the plans,
specifications, estimates, bids and contracts; and such extra work shall be performed by the
contractor at the direction of the engineer at cost of labor and materials and overhead including
superintendence as set forth in the plans, specifications, or construction contract, such amount to
be included in the assessment for the project (but not exceeding in the aggregate the estimated
maximum special benefits to any tract so assessed) or to be paid out of the general or other funds
of the district available therefor, in the discretion of the board.