Colorado Code § 30-28-136

Referral and review requirements
Open in Lexace · Ask the AI about this section
(1) Upon receipt of a complete
preliminary plan submission, the board of county commissioners or its authorized representative
shall distribute copies of prints of the plan as follows:
(a) To the appropriate school districts;
(b) To each county or municipality within a two-mile radius of any portion of the
proposed subdivision;
(c) To any utility, local improvement and service district, or ditch company, when
applicable;
(d) To the Colorado state forest service, when applicable;
(e) To the appropriate planning commission;
(f) To the local conservation district board within the county for explicit review and
recommendations regarding soil suitability, floodwater problems, and watershed protection.
Such referral shall be made even though all or part of a proposed subdivision is not located
within the boundaries of a conservation district.
(g) When applicable, to the county or district public health agency or the state
department of public health and environment for its review of the on-lot sewage disposal reports,
for review of the adequacy of existing or proposed sewage treatment works to handle the
estimated effluent, and for a report on the water quality of the proposed water supply to serve the
subdivision. The department of public health and environment or county or district public health
agency to which the plan is referred may require the subdivider to submit additional engineering
or geological reports or data and to conduct a study of the economic feasibility of a sewage
treatment works prior to making its recommendations. No plan shall receive the approval of the
board of county commissioners unless the department of public health and environment or
county or district public health agency to which the plan is referred has made a favorable
recommendation regarding the proposed method of sewage disposal.
(h) (I) To the state engineer for an opinion regarding material injury likely to occur to
decreed water rights by virtue of diversion of water necessary or proposed to be used to supply
the proposed subdivision and adequacy of proposed water supply to meet requirements of the
proposed subdivision. If the state engineer finds such injury or finds inadequacy, he shall express
such finding in an opinion in writing to the board of county commissioners, stating the reason for
his finding, including, but not limited to, the amount of additional or exchange water that may be
required to prevent such injury. In the event the subdivision is approved notwithstanding the
state engineer's opinion, the subdivider shall furnish to all potential purchasers a copy of the state
engineer's opinion prior to the sale or a synopsis of the opinion; except that the subdivider need
not supply the potential purchaser with a copy of such opinion or synopsis if, in the opinion of
the board of county commissioners, the subdivider has corrected the injury or inadequacy set
forth in the state engineer's finding.
(II) A municipality or quasi-municipality, upon receiving the preliminary plan
designating said municipality or quasi-municipality as the source of water for a proposed
subdivision, shall file, with the board of county commissioners and the state engineer, a
statement documenting the amount of water which can be supplied by said municipality or
quasi-municipality to proposed subdivisions without causing injury to existing water rights. The
state engineer shall file, with said board of county commissioners, written comments on the
report. If, in the judgment of the state engineer, the report is insufficient to issue an opinion, the
state engineer shall notify the board of county commissioners to this effect, indicating the
deficiencies.
(i) To the Colorado geological survey for an evaluation of those geologic factors that
would have a significant impact on the proposed use of the land; except that, upon written
request from the board of county commissioners or the board's authorized representative, the
Colorado geological survey may exempt any preliminary plan from this referral and review
requirement.
(2) The agencies named in this section shall make recommendations within twenty-one
days after the mailing by the county or its authorized representative of such plans unless a
necessary extension of not more than thirty days has been consented to by the subdivider and the
board of county commissioners of the county in which the subdivision area is located. The
failure of any agency to respond within twenty-one days or within the period of an extension
shall, for the purpose of the hearing on the plan, be deemed an approval of such plan; except
that, where such plan involves twenty or more dwelling units, a school district shall be required
to submit within said time limit specific recommendations with respect to the adequacy of school
sites and the adequacy of school structures.
(3) The provisions of this part 1 shall not modify the duties or enlarge the authority of
the state engineer or the division engineers nor divest the water courts of jurisdiction over
actions concerning water right determinations and administration; neither shall any opinion of
the state engineer submitted under subsection (1)(h) of this section nor any finding by a board of
county commissioners concerning subdivision water supply matters create any presumption
concerning injury or noninjury to water rights; and neither the state engineer's opinion nor the
finding of the board of county commissioners may be used as evidence in any administrative
proceeding or in any judicial proceeding concerning water right determinations or
administration.
(4) Repealed.