Colorado Code § 25-7-118

Delayed compliance orders
Open in Lexace · Ask the AI about this section
(1) The division may, after notice and an
opportunity for a public hearing, issue an order for any stationary source which specifies a date
for final compliance with any requirement of the state implementation plan not later than the
date for attainment of any national ambient air quality standard specified in such plan and in no
event longer than one year after the date the order was issued, if the requirements of this section
are met. If a public hearing is requested by an interested person, the request shall, within twenty
days of its receipt, be transmitted to the commission. The commission shall, within sixty days of
its receipt of the request, hold a public hearing with respect thereto and, within thirty days of
such hearing, issue its decision and order.
(2) An order pursuant to this section may be issued if the order:
(a) Is issued after notice to the public containing the content of the proposed order and
after an opportunity for a public hearing thereon;
(b) Contains a schedule and timetable for compliance which requires final compliance as
expeditiously as practical, but in no event later than July 1, 1979, or three years after the date for
final compliance with such requirement that is specified in the state implementation plan,
whichever is later;
(c) In the case of a major stationary source, notifies the source that it will be required to
pay a penalty under section 25-7-115 in the event such stationary source fails to achieve final
compliance by July 1, 1979, or by such later date as is specified in the order in accordance with
section 25-7-115;
(d) Requires emission monitoring and reporting by the stationary source;
(e) Requires the stationary source to use the best practical system of emission reduction
for the period during which such order is in effect and requires the stationary source to comply
with such interim requirements as the division or commission determines are reasonable and
practical.
(3) If any stationary source not in compliance with any requirement of the state
implementation plan gives notice to the division or commission that such stationary source
intends to comply by means of replacement of the facility, a complete change in its production
process, or a termination of its operations, the division or commission may issue an order under
this section permitting the stationary source to operate until July 1, 1979, without any interim
schedule of compliance. As a condition of the issuance of any such order, the owner or operator
of such stationary source shall post a bond or other surety in an amount equal to the cost of
actual compliance by such facility and any economic value which may accrue to the owner or
operator of such stationary source by reason of the failure to comply. If the owner or operator of
a stationary source for which the bond or other surety required by this subsection (3) has been
posted fails to replace the facility, change the production process, or terminate the operations as
specified in the order by the required date, the owner or operator shall immediately forfeit on the
bond or other surety, and the commission shall have no discretion to modify the order under this
subsection (3) or to compromise the bond or other surety.
(4) Any order pursuant to this section shall be terminated if the commission determines,
after notice and a hearing, that the inability of the stationary source to comply no longer exists. If
the owner or operator of the stationary source to which the order is issued demonstrates that
prompt termination of such order would result in undue hardship, the termination shall become
effective at the earliest practicable date on which such undue hardship would not result but in no
event later than the date required under this section.
(5) (a) If, on the basis of any information available to it, the division has reason to
believe that a stationary source to which an order has been issued pursuant to this section is in
violation of any requirement of such order or of any provision of this section, it shall notify the
commission and the owner or operator of the alleged violation and may revoke such order or
may commence an appropriate enforcement action pursuant to this article, or both.
(b) The owner or operator shall respond as provided in section 25-7-115, and, within
sixty days after receipt of such notice, the division shall issue a determination thereon. If the
division determines that the stationary source is in violation of any requirement of such order or
of any provision of this section, it shall revoke such order and enforce compliance with the
requirement with respect to which such order was granted or shall order payment of a penalty as
provided in section 25-7-115, or both.
(6) During the period of the order issued under this section and when the owner or
operator is in compliance with the terms of such order, no other enforcement action pursuant to
this article shall be taken against such owner or operator based upon noncompliance during the
period the order is in effect with the requirement for the stationary source covered by such order.
(7) Nothing in this section, and no delayed compliance order granted pursuant to this
section, shall be construed to prevent or limit the application of the emergency provisions of
section 25-7-112 or 25-7-113. No order issued under this subsection (7) shall prevent the state
from assessing penalties nor otherwise affect or limit the state's authority to enforce under other
provisions of this article.

‹ Prev All Colorado sections Next ›


Lexace provides legal information, not legal advice, and no attorney–client relationship is created. Statute text is provided for general information and may not reflect the most recent amendments; verify against the official state code.