Colorado Code § 24-91-104

Contract - completion by public entity - partial payments
Open in Lexace · Ask the AI about this section
If it becomes
necessary for a public entity to take over the completion of any contract, all of the amounts
owing the contractor, including the withheld percentage, shall be applied: First, toward the cost
of completion of the contract; second, toward performance of the public entity's withholding
requirement set forth in section 38-26-107, C.R.S.; third, to the surety furnishing bonds for the
contract work, to the extent such surety has incurred liability or expense in completing the
contract work or made payments pursuant to section 38-26-106, C.R.S.; then, to the contractor.
Such retained percentage as may be due any contractor shall be due and payable at the expiration
of thirty days from the date of final acceptance by the public entity of the contract work.