(a) Each public utility electrical corporation shall develop and offer its customers, on or before May 30, 2001, the opportunity to participate, in addition to other programs developed by the commission, in a demand reduction program as described in this section. (b) The program required by this section shall identify specific periods coincident with morning or evening system peak conditions determined by the Independent System Operator within which the customer agrees to drop a preset amount of load. This program shall be known as the Scheduled Load Reduction Program. The commission shall develop appropriate incentives for customers to participate in the program.