California Civil Code § 8814

Civil Code
Open in Lexace · Ask the AI about this section
(a) If a direct contractor has withheld a retention from one or more subcontractors, the direct contractor shall, within 10 days after receiving all or part of a retention payment, pay to each subcontractor from whom retention has been withheld that subcontractor’s share of the payment. (b) If a retention received by the direct contractor is specifically designated for a particular subcontractor, the direct contractor shall pay the retention payment to the designated subcontractor, if consistent with the terms of the subcontract. (c) If a good faith dispute exists between the direct contractor and a subcontractor, the direct contractor may withhold from the retention to the subcontractor an amount not in excess of 150 percent of the estimated value of the disputed amount.

‹ Prev All California sections Next ›


Lexace provides legal information, not legal advice, and no attorney–client relationship is created. Statute text is provided for general information and may not reflect the most recent amendments; verify against the official state code.