Arizona Code § 28-6806

Toll road construction and completion
Open in Lexace · Ask the AI about this section
28-6806. Toll road construction and completion
A. Construction of the toll road shall begin within thirty days after the date of the order approving the application and shall continue with all reasonable dispatch until completed.
B. When the road is completed, the owner of the franchise shall file with the county recorder a certificate that the road is completed and conforms to the requirements of law.

‹ Prev All Arizona sections Next ›


Lexace provides legal information, not legal advice, and no attorney–client relationship is created. Statute text is provided for general information and may not reflect the most recent amendments; verify against the official state code.