Mr. Justice Brandéis delivered the opinion of the court, Spearin brought this suit in the Court of Claims, demanding a balance alleged to be due for work done under a contract to construct a dry-doek and also damages for its annulment. Judgment was entered for him in the sum of $141,180.86;' (51 Ct. Clms. ,155) and both parties appealed to this court. The Gov…