Port of Seattle v. Pollution Control Hearings Board

Supreme Court of Washington · Decided 2004-05-14

Cited by 225 later decision(s) in our corpus · see the citation network in Lexace

Open in Lexace · Ask the AI about this case

From the opinion

Bridge, J. Construction of the third runway at the Seattle-Tacoma International Airport (SeaTac) will require placing fill into area wetlands. Before the Army Corps of Engineers may issue a permit to fill wetlands, the project proponent must obtain certification from the State, pursuant to § 401 of the Clean Water Act ( 33 U.S.C. § 1341 ), stating that there is reasonable assurance that the pro…

Read the full opinion (source) ↗