The opinion of the court was delivered by Ackerson, J. On July 2, 1948, the Elintkote Company was the owner of a building, referred to as the CiLiquid Storage Plant,” then in the final stages of construction. The Lummus Company, as general contractor for the owner, had subcontracted the electrical work to Buhl Caffrey, Inc. On that day the plaintiff, Joh…