From the opinion

Callahan, J. This is a contract action brought pursuant to General Statutes § 49-42 1 by the plaintiff, The *470 Nor’easter Group, Inc. (Nor’easter), a subcontractor, to recover a balance due for labor and material furnished in the construction of a municipal swimming pool for the city of Torrington. The action was brought on a payment bond agai…