SCHALL, Circuit Judge. The United States appeals from the June 26, 1992 judgment of the United States Claims Court. 1 Following a trial, the Claims Court (i) awarded Melvin Wilner, d/b/a Wil-ner Construction Company (Wilner), an additional $26,271.49 plus interest on his claim for delay compensation under the Contract Disputes Act of 1978 (CDA), 41 U.S.C. §§ 601-613<…