Mr. Chief Justice Warren delivered the opinion of the Court. The question in these cases is whether the Federal Power Commission has gone beyond the scope of its delegated authority in denying a certificate of public convenience and necessity under § 7 (e) of the Natural Gas Act of 1938, 52 Stat. 821 , as amended, 15 U. S. C. § 717 et s…
Read the full opinion (source) ↗