City of Corpus Christi v. Public Utility Commission of Texas

Supreme Court of Texas · Decided 2001-08-30

Cited by 225 later decision(s) in our corpus · see the citation network in Lexace

Open in Lexace · Ask the AI about this case

From the opinion

Justice OWEN, joined by Chief Justice PHILLIPS, Justice HECHT, Justice ENOCH, Justice BAKER, Justice ABBOTT, Justice HANKINSON, and Justice JEFFERSON, concurring. I The Public Utility Regulatory Act (PURA) first came into being in 1975. At that time, the Legislature established a comprehensive regulatory system for electric utilities. 1 The Legislature had co…

Read the full opinion (source) ↗


Lexace provides legal information, not legal advice, and no attorney–client relationship is created. Citation figures are counts of later citing opinions in our corpus and may be incomplete; always read and Shepardize the full opinion before relying on it.