Berschauer/Phillips Construction Co. v. Seattle School District No. 1

Supreme Court of Washington · Decided 1994-10-06

Cited by 208 later decision(s) in our corpus · see the citation network in Lexace

Open in Lexace · Ask the AI about this case

From the opinion

Guy, J. We granted review to decide whether a general contractor may recover in tort $3.8 million in economic dam-ages for construction delays against an architect, a structural engineer and a project inspector, none of whom were in privity of contract with the general contractor. The Superior Court held the economic loss rule does not allow a general contractor to recover purely eco…